Photographs are uploaded every two weeks showing the progress in construction of the Japan Pavilion.
2009 December 26
Construction on the Pavilion finished. Completion ceremony held.
2009 December 14
Construction of the steel frame for the Event Hall (extreme left) has been completed.
2009 November 30
Installation of the outer coating on the roof of the Eco-tubes has been almost completed.
2009 November 15
Installation of the outer coating has begun on the east face.
2009 October 31
Jacking-down work on the steel frame in the roof has been completed.
2009 October 16
Assembly work on the steel frame in the roof has been almost completed.
2009 September 30
Construction of the steel frame in the roof has entered its final stages.
2009 September 15
Construction of steel frames for Eco-tubes No. 1–No. 6
2009 August 31
Construction of steel frames for Eco-tube No. 4 and fourth floor
2009 August 16
Construction of steel frame for upper part of theater begun
2009 July 31
Concrete poured for second floor
2009 July 15
Concrete poured for second floor
2009 June 30
Construction of steel frame for roof begun
2009 June 15
Assembly of external scaffolding begun
2009 May 31
External backfilling begun
2009 May 12
Construction of steel frame begun
2009 April 30
Mat foundation poured
2009 April 15
Crane foundation construction begun
2009 March 31
Ground improvement work to begin soon
2009 March 15
Preparations for construction work completed
2009 February 17
Handover of the Japan Pavilion plot from the Bureau of Shanghai World Expo Coordination